19A NCAC 02D .0806      INTERPRETATION OF QUANTITIES IN PROPOSAL FORM

(a)  The quantities appearing in the proposal are approximate only and shall be used for the comparison of bids.  Payment to the contractor shall be made only for the actual quantities of the various items that are completed and accepted in accordance with the terms of the contract.

(b)  When quantities are shown for items to be bid on a lump sum basis, these quantities are furnished for the convenience of bidders, and the Department shall not be responsible for, nor guarantee as correct, any quantity given.

 